INFRASTRUCTURE & UTILITIES WORK FOR TWO PRODUCTION WELLS AT WA’AD AL SHAMAL WELL FIELD
Location: Turaif
Value: 42,400,000 SAR
EPC: Kettaneh Construction
Client: Ma'aden
Brief Project Details:
Piping: Process well pumps system including piping, power, instrumentation, and communication to the central control building
Building Works: Two electrical substations with civil works, HVAC, fire protection and detection, lighting, power, earthing, telecommunication, and instrumentation
Completion Period: 10 months (January 2020 to October 2020)