Power Station, Zouk
Scope of Work - Highlights
Excavation: 70,000 cu m
Reinforced Concrete: 17,000 cu m
Reinforced Steel: 2,000 tons
Power: 172 Megawatt
Kettaneh Construction carried out the civil engineering work of the project. The work comprised construction of the machine hall, bases for the turbo-generating unit, boiler house, cable tunnel, transformers area, cooling water circulating system, fuel storage, ancillary building and a 150 m high chimney.